Our Latest Posts
July 2018 - New Inlet Pipe & Flow Meter
The inlet pipe to the clarifier tanks has now been renewed, and a flow meter installed, raw water will be pumped up through this meter from Juas reservoir to begin the treatment process.
11 Jul 2018
July 2018 - Cleared Filter Beds
The filter beds now looking clear and clean with new pipework in place. They are awaiting the installation of new nozzles before being refilled with a combination of sand and anthracite prior to recommissioning of the works.
July 2018 - New Floats
New floats these will float on Juas Reservoir above the low lift pumps which will be suspended 4 metres below. These pumps will feed water from the reservoir to the clarifier tanks where the water treatment process begins.
May 2018 - Analytical equipment in place
Some of the sites Analytical equipment fitted in place, this equipment will monitor Chlorine, PH and Turbidity.