January 2018 - Chemical Store
A very full chemical store following delivery of control panels for the high lift house. Wiring by our electrician Rhys continues along with the plumbing in of dosing equipment within the chemical store by our fitter Liam.
12 Apr 2018
January 2018 - Plinth Shuttering
A misty day over Juas but the work must go on! Shuttering is now in place for the concrete plinth where the standby generator will sit.
November 2017 - Chemical Storage Tanks
Storage tanks in place for Poly aluminium chloride, (PACl) this coagulant is added to the incoming raw water in the clarifier tank. This storage tank has a maximum capacity of 5,000 litres.
November 2017 - The Poly Electrolyte Plant
This is the Poly Electrolyte make up plant, this plant makes and stores chemical on demand and will be connected to chemical dosing pumps. Poly Electrolyte is used as a flocculent aid and will be added to incoming raw water.